making of 

  • Creating and presenting a model, if required

  • Welding of a solid substructure

  • Fixing nets on the substructure

  • Spraying of the base layer

  • Sculpting of the mortar in the second layer

  • Application of the patina or paint
     

Model
Creating and presenting a model, if required
Startup
Welding supporting structure
Welding base construction
Fixing nets on the substructure
Spraying of the base layer
Spraying of the base layer
Spraying of the end layer
Sculpting of the mortar in the secon
Sculpting of the mortar in the secon
Application of the patina or paint
Show More